/ ENERGY TRENDS
    
  
Sun, 01 Nov 2009 09:54:00

AfDB Approves €153M for Botswana Power Project

AfDB has approved a loan of €153 million ($226.4 million) to the Government of Botswana, to finance specific components of the Morupule B power station. The total estimated project cost is US$1.4 billion and AfDB is providing 15%, China’s ICBC Standard Bank (59%), Government of Botswana (15%) and World Bank (11%).
Total estimated project cost is US$1.4 billion and AfDB is providing 15%, China’s ICBC Standard Bank (59%), Government of Botswana (15%) and World Bank (11%). Photo: Morupule Power B Project; China National Electric Equipment Corp (CNEEC).
The African Development Bank (AfDB) Group Board of Directors on Wednesday, 28 0ctober 2009 in Tunis, approved a loan of €153 million to the Government of Botswana, to finance specific components of the Morupule B power station and associated transmission infrastructure.

The project involves the construction of a 600-MW (4 x 150 MW) coal fired power plant and associated transmission infrastructure. The Morupule B plant will be located adjacent to the existing Morupule A plant, and connected to the national grid by two new transmission lines.

Designed to help the country achieve energy self-sufficiency, the project will, on completion, support economic growth and reduce poverty. Botswana has, until now, relied on the importation of electricity to meet its growing demand (500 MW in 2008 and around 600 MW projected for 2012). In 2008, 80% of the electricity supplied in Botswana consisted of imports from neighbouring countries, notably from South Africa. The remaining 20% was generated by the country’s Morupule A, a 25-year-old plant.

However, as a result of the acute energy crisis in the region, neighbouring countries are rapidly reducing exports to Botswana, and the country has been forced to resort to load shedding since 2008. Imports will be further reduced in coming years and are expected to be fully discontinued by 2013.

The Morupule B project will help in the realization of the government’s strategy to increase household access rates from 47% to 80% by 2016. The project will also be beneficial to the region as a whole, since it will enable Botswana to become a net energy exporter by 2014.

The project is estimated at US$ 1.4 billion (UA 905.4 million). The AfDB is providing 15% of the project cost. The other contributors include China’s ICBC Standard Bank (59%), the Government of Botswana (15%) and the World Bank (11%).

As an upper-middle income country, most of Botswana’s traditional donors had reduced the level of their assistance to the country. It is only recently, due fiscal deficit stemming from a contraction in economic activity, that the government started re-engaging with Development Finance Institutions (DFIs) for support. It is in this context that the AfDB approved a US$ 1.5 billion Economic Diversification Support Loan to the country in June 2009, the largest loan ever granted by the Bank.

Related Link
Morupule Power B Project

Follow us on

http://twitter.com/thegreeneconomy

 ENERGY FRONTLINES! INNOVATIVE DIVES
€400bn Energy Plan to Harness African Sun

It's decision day on a chain of solar generators across the desert that could supply a quarter of...

Modelling Energy Scenarios for Ghana and...

Assessing Policy Options for Increasing the Use of Renewable Energy for Sustainable Development:...

Sustainable Bioenergy: A Framework for...

This publication seeks to structure the approach to the current discussion on bioenergy....

Energy Challenge for Achieving the MDGs

This report emphasizes the centrality of providing energy services in the pursuit of the MDGs. It...

Energy in the UN: An Overview of UN-Energy...

This publication showcases the work of UN-Energy members in the various fields and explains the...



© 2009 Green Economy Initiative  Tracking Investments in Green Economy, Green Jobs and Clean Technologies. All Rights Reserved.